most of this is our fault.
we didn't order enough flooring - expected delivery date = 5 march.
sadly, this is gating the stove installation.
we didn't order enough cabinet 'toe kit'.
happily, this gates nothing.
the counter-top arrived wednesday - it was not the style we ordered (it WAS the right pattern).
re-work will take till next tuesday.
on the bright side: we expect windowsills to be installed same day.
more 'on the bright side': all window-dressings have arrived.
we picked up new door today.
the original 3-week estimate has been extended somewhat...
in the best of all possible worlds, we'll have a kitchen by 1st or 2nd week of march.
Astrid Et Raphaƫlle: PBS Has A Hit On Its Hands
3 hours ago
No comments:
Post a Comment